MHF Foam Suppression System Upgrade

Key Capabilities

  • Civil works & site construction

  • Piping systems—supply & installation

  • Project management & construction coordination

  • Major Hazard Facility execution

  • Commissioning & system handover

Overview

Vecta engineered and delivered the upgrade of a critical foam fire suppression system at a Melbourne petroleum distribution terminal, a Major Hazard Facility. The works included civil, mechanical and piping construction, installation of pumps, tanks and structural steelwork, commissioning support and demolition of redundant equipment. Through careful planning of tie-ins and outages, Vecta completed the project safely while maintaining fire protection and operational continuity.